News 2022

Volcanic files NI 43-101 technical report for Initial Resource Estimate at Holly Project, Guatemala

Jul 27, 2022 Download PDF

News Release
Shares issued 45,551,210
VG close - C$0.23
W/C +$6.5 million cash

Vancouver, British Columbia – Volcanic Gold Mines Inc. (TSXV-VG) (“Volcanic” or “the Company”) is pleased to advise that it has filed on SEDAR a NI 43-101 technical report in support of the recently announced maiden Inferred Mineral Resource Estimate for the Holly property, Guatemala (see news release June 9, 2022). The mineral resource estimate is effective June 7, 2022 and is reported in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum Definition ‎Standards (2014) incorporated by reference in National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

Highlights

  • A maiden Inferred Mineral Resource has been estimated for the first target, La Peña vein at the Holly project, Guatemala.
  • The high grade La Peña vein remains open to expansion along strike and importantly at depth, where exceptionally high grade results have been returned.
  • Multiple other drill targets remain un-tested at Holly with potential for new discoveries.

Table 1: Holly, Peña Vein Resource Estimate
(Effective date 7th June, 2022)

Category

Cut-off grade AuEq(2) (g/t)

Tonnes above cutoff (millions)

Gold (g/t)

Silver (g/t)

Gold (oz)

Silver
(oz)

Gold Equivalent(2) (g/t)

Gold Equivalent(2) (oz)

Inferred

3.00

1.32

6.46

256

272,110

10,913,360

9.57

406,316

Notes:

  1. Resources estimated using a 3.0 g/t Gold equivalent cut-off grade and a top cap grade of 100 g/t Gold and 2,000 g/t Silver and presented on a 100%-basis
  2. Gold Equivalent Au(eq) values based on Au US$1800 and Ag US$22 using formula (Au g/t + (Ag g/t*0.01222))
  3. Mineral Resources which are not Mineral Reserves have not demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues. The mineral resources in this report were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum standards on mineral resources and reserves, definitions, and guidelines prepared by the CIM standing committee on reserve definitions and adopted by the CIM council. Notwithstanding, to meet the requirement that the reported Mineral Resources show “reasonable prospects for eventual economic extraction”.
  4. The quantity and grade of reported Inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as an Indicated or Measured Mineral Resource. It is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.
  5. Contained metal and tonnes figures in totals may differ due to rounding.
  6. A technical report regarding the mineral resource estimation for the project will be filed by Volcanic on SEDAR within 45 days.

The Mineral Resource Estimate is underpinned by data from 21 diamond drillholes totalling 3707m of drilling. Drill spacing ranges between 20 and 100m. All sample data was composited to a 2D dataset (linear grade and true thickness values) prior to analysis and estimation. The sample database and the topographic survey were reviewed and validated by Bruce Smith, Ludving Monroy and Shawn Rastad prior to being supplied to John Arthur, an independent UK based Resource Consultant. Such review and validation help to support the reliability of the estimate. Geological domain modelling was completed by Bruce Smith and Dr John Arthur. Mineral Resource domain modelling, grade interpolation, Mineral Resource classification and reporting of the Mineral Resource statement, was performed by Dr John Arthur. Dr Arthur, Mr Smith, Mr Monroy and Mr Rastad are “qualified persons” within the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). Block modelling was carried out using cell dimensions of 32mE by 32mN by 8 mRL and was coded to reflect the surface topography and mineralised zones. Density values were globally assigned into two zones, an upper zone between 50 to 100m from surface had an average density of 2.33t/m³ and below this an average density of 2.52t/m³ was applied. The Mineral Resource Estimate has been classified based on data density, data quality, confidence in the geological interpretation and confidence in the robustness of the grade interpolation.

Technical Information

Bruce Smith, M.Sc. (Geology), a member of the Australian Institute of Geoscientists, is Volcanic’s Qualified Person as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects. Mr. Smith has 28 years of mineral exploration experience and has prepared and approved the technical information contained in this news release.

Quality Assurance and Quality Control

Volcanic follows industry standard procedures for diamond core drilling and analysis. Drilling is carried out using NQ and HQ size tooling. Drill core is cut in half using a rock saw with one-half of the core then taken as a sample for analysis. Sample intervals are generally 1m intervals, producing samples of between 2 to 9 kg. Half-core samples were initially processed at a Volcanic Gold preparation facility. The half core samples underwent primary crushing and split to produce a 250g sample under the supervision of a company geologist and qualified person. The split sample was then air shipped to certified ALS laboratories in Vancouver for further preparation and assay. All samples are fire assayed for Au and are analyzed for Ag and multi-elements using method code ICP following a four-acid digestion. Overlimits are analyzed using an appropriate method. Multi-element geochemical standards and blanks are routinely entered into the drill core sample stream to monitor laboratory performance. Quality control samples submitted were returned within acceptable limits.

Terms of Guatemala Radius Gold and Volcanic Gold Mines option

Pursuant to an option agreement signed in May 2020 with Radius Gold Inc. (TSXV: RDU), Volcanic can earn a 60% interest in the Holly and Banderas projects by spending the cumulative amount of US$7.0 million on exploration of the properties within 48 months from the date of the agreement. In accordance with the Option terms, Volcanic spent an initial US$1M on exploration within the 12 months of receiving the required drill permits, which expenditures included a minimum 3,000m of drilling on the properties.

Following the exercise of the Option, Volcanic will enter into a standard 60/40 Joint Venture in order to further develop the Properties. Volcanic has also been granted an exclusive right to evaluate all other property interests of Radius in Guatemala with a right to acquire an interest in any or all other such properties on reasonable terms.

About Volcanic

Volcanic brings together an experienced and successful mining, exploration and capital markets team focused on building multi-million-ounce gold and silver resources in underexplored countries. Through the strategic acquisition of mineral properties with demonstrated potential for hosting gold and silver resources, and by undertaking effective exploration and drill programs, Volcanic intends to become a leading gold-silver company.

For further information, visit our website at www.volgold.com.

Volcanic Gold Mines Inc.

Simon Ridgway, President and CEO

Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Forward-looking statements

Certain statements contained in this news release constitute forward-looking statements within the meaning of Canadian securities legislation. All statements included herein, other than statements of historical fact, are forward- looking statements and include, without limitation, statements about the Company’s plans for its property interests in Guatemala. Often, but not always, these forward looking statements can be identified by the use of words such as “estimate”, “estimates”, “estimated”, “potential”, “open”, “future”, “assumed”, “projected”, “used”, “detailed”, “has been”, “gain”, “upgraded”, “offset”, “limited”, “contained”, “reflecting”, “containing”, “remaining”, “to be”, “periodically”, or statements that events, “could” or “should” occur or be achieved and similar expressions, including negative variations.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by forward-looking statements. Such uncertainties and factors include, among others, the uncertainties inherent in the mineral resource estimates; whether the Company’s planned exploration work will be proceed as intended; changes in general economic conditions and financial markets; the Company or any joint venture partner not having the financial ability to meet its exploration and development goals; risks associated with the results of exploration and development activities, estimation of mineral resources and the geology, grade and continuity of mineral deposits; unanticipated costs and expenses; and such other risks detailed from time to time in the Company’s quarterly and annual filings with securities regulators and available under the Company’s profile on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward-looking statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to: that the Company’s stated goals and planned exploration and development activities will be achieved; that there will be no material adverse change affecting the Company or its properties; and such other assumptions as set out herein. Forward-looking statements are made as of the date hereof and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on forward-looking statements.